Uganda development projects tracker
32 major projects in Uganda (oil and gas, power, transport, water, health, digital and more), each with its status, stated cost, target year and sources. Updated 3 October 2026.
- First commercial oil target moved to June 2027: delayed, target 2027. Albertine Graben (Lake Albert region) In September 2026 the Finance Minister and officials from PAU, UNOC, NPA and URA told Parliament's Finance Committee that first commercial oil is now expected before the end of June 2027. The July 2026 target passed without commercial crude production. Earlier targets in 2018, 2020 and 2025 were also missed.
- Tilenga oil project: under construction, target 2027. Buliisa and Nwoya districts, north of Lake Albert; CPF at Kasenyi, Ngwedo, Buliisa Tilenga is the TotalEnergies-operated upstream oil project in Buliisa and Nwoya districts, with a central processing facility at Kasenyi, Buliisa. Officials told Parliament it was 67% complete in March 2026; the Daily Monitor put it at over 70% in August 2026. First oil is now expected before the end of June 2027.
- Kingfisher oil project: under construction, target 2027. Buhuka flats, Kikuube District, Lake Albert Kingfisher is the CNOOC-operated oil field on the Buhuka flats in Kikuube District, on the shore of Lake Albert. Officials told Parliament it was 77% complete in March 2026, while the Daily Monitor reported more than 90% in August 2026. Reported progress figures vary by measure and date.
- East African Crude Oil Pipeline (EACOP): under construction, stated cost USD 5.0 billion, target 2026. Kabaale (Hoima) to Tanga, Tanzania EACOP is a 1,443 km heated crude oil pipeline from Kabaale, Hoima, to Tanga port in Tanzania, crossing ten Ugandan districts. By September 2026, 1,414 km had been completed and buried, and the pipeline was expected to be ready to receive crude by mid-December 2026. Outstanding work includes pump stations three and four and electrical, instrumentation, telecoms and security systems.
- Uganda (Kabaale) oil refinery: planned, stated cost USD 4.0 billion, target 2030. Kabaale, Buseruka Sub-County, Hoima District A planned 60,000 barrels-per-day refinery at Kabaale, Hoima District, costing about USD 4bn. Under the March 2025 implementation agreement, UAE-based Alpha MBM Investments holds 60% and UNOC 40%. Front-end engineering design is under way, the final investment decision is now expected in the first quarter of 2027, and commissioning is projected for 2029-2030.
- Kabalega (Hoima) International Airport: delayed, target 2026. Kabaale, Hoima District Kabalega International Airport at Kabaale, Hoima, was started in 2018 to serve the oil region. Nile Post reported it at 98% complete in June 2026, a level unchanged since 2023, with a generator, fire trucks and control tower equipment still to be installed. The Prime Minister directed SBC Construction and the Ministry of Works to finish it by December 2026, ahead of AFCON 2027.
- Karuma Hydropower Plant (600 MW): operational, stated cost USD 1.7 billion, target 2024. Karuma, Kiryandongo District The 600 MW Karuma plant on the Kyoga Nile has six 100 MW units. It began commercial operation on 12 June 2024 and President Museveni commissioned it on 26 September 2024. It was built by Sinohydro from 2013, at a cost of about USD 1.7bn, with a USD 1.4bn China Exim Bank loan.
- Isimba Hydropower Plant spillway rehabilitation: operational, stated cost USD 568 million. Victoria Nile, between Kayunga and Kamuli districts The 183 MW Isimba plant on the Nile was commissioned in March 2019 at a cost of about USD 567.7m, built by China International Water & Electric Corporation (CWE). In March 2026 UEGCL met CWE to plan rehabilitation of the spillway system, ranging from emergency repairs to long-term fixes, and urged the contractor to mobilise quickly.
- Nyagak III Hydropower Plant (6.6 MW): operational, stated cost USD 20 million, target 2025. Zombo District, West Nile The 6.6 MW Nyagak III plant in Zombo District was commissioned on 1 August 2025 by Energy Minister Ruth Nankabirwa. It cost about USD 20m and was built as a public-private partnership between UEGCL, Hydromax and DOTT Services through Genmax Nyagak Ltd.
- Buyende nuclear power plant site study: planned, target 2031. Kasaato, Kidera Sub-county, Buyende District In May 2025 the Ministry of Energy signed a 26-month contract with Korea Hydro & Nuclear Power, with Dohwa Engineering and KEPCO E&C, to evaluate a site at Kasaato village, Kidera Sub-county, Buyende District. Backup sites are in Nakasongola and Kiruhura. The study runs until July 2027 and will propose a layout for four APR1400 reactors. Uganda's long-term plan is 8,400 MWe by 2040.
- Standard Gauge Railway: Malaba-Kampala: under construction. Malaba (Tororo) to Kampala Yapi Merkezi signed a EUR 2.7bn contract in October 2024 for the 272 km electrified Malaba-Kampala line, and President Museveni launched construction in Tororo on 21 November 2024. By August 2026 only preparatory works were under way: designs, construction camps, access roads, a sleeper factory and batching plants. The Islamic Development Bank has approved EUR 650.75m, and government is targeting financial close by November 2026.
- Kampala-Jinja Expressway (PPP): delayed, stated cost USD 1.4 billion. Kampala to Jinja via Mukono This is a planned tolled expressway of about 95 km between Kampala and Jinja, including the Kampala Southern Bypass, to be delivered as a public-private partnership. The AfDB signed a USD 229.5m loan in 2021 and the project cost is estimated at about USD 1.4bn. Only one consortium submitted a bid at the March 2025 bid opening; we found no public record of a contract award or construction start by October 2026.
- Kampala Flyover Project: completed, stated cost USD 81 million, target 2025. Clock Tower, Nsambya and Kibuli, Kampala Lot 1 was commissioned by President Museveni on 5 March 2025. It includes the 584 m Clock Tower flyover, the 375.8 m Nsambya underpass, three pedestrian bridges and 3,190 m of widened roads, cost USD 81m and was financed by JICA. A second phase covering Kitgum House, Garden City and the Jinja Road junctions was planned to start construction in 2026.
- Entebbe International Airport expansion: under construction, target 2026. Entebbe, Wakiso District UCAA said a new 20,000 sq m passenger terminal would open in phases from January 2026. It adds three aerobridges (five in total), 24 check-in counters and 14 self-check-in counters, and lifts capacity from 2 million to at least 3.5 million passengers a year. International traffic for January to November 2025 (2,247,145) already exceeded the 2024 total.
- Uganda Airlines route and fleet expansion: operational. Entebbe International Airport Uganda Airlines will start flights to Accra on 27 October 2026 and Kigali on 18 November 2026. Government has ordered eight Boeing aircraft, four 737s and four wide-bodies, funded from the budget. Nile Post reported in August 2026 that nearly 60% of the fleet was grounded for engine maintenance, including two Airbus A330s.
- Busega-Mpigi Expressway: delayed, target 2029. Busega (Kampala) to Mpigi This is a 27.3 km expressway from Busega in Kampala to Mpigi on the Northern Corridor towards Rwanda. In November 2025 the AfDB approved an additional EUR 217m after land disputes stalled works. The cost of the Ugandan section rose to about EUR 424m. Works were to resume in January 2026, with completion planned for December 2029 and full project close in 2030.
- Kiira Vehicle Plant and Kampala electric buses: operational. Jinja (plant); Kampala (bus service) The Kiira Vehicle Plant on a 100-acre site in Jinja was commissioned on 7 October 2024, with an initial capacity of 2,500 vehicles a year that is planned to rise to 5,000. In June 2026 eight Kiira electric buses were running in Kampala. KCCA was assessing the plant, with a target of at least 100 e-buses by the end of 2026 and buses for a future BRT.
- Lubowa International Specialised Hospital: delayed, target 2026. Lubowa, Wakiso District The Lubowa hospital project began in 2019 with an original completion date of June 2021. In April 2026 the Health Minister told Parliament it was 70% complete and targeted for December 2026, and government sought UGX 100bn to make it operational. The total cost is about UGX 1.3-1.4 trillion; Pulse reported UGX 723.75bn spent by December 2025.
- Katosi water network expansion (Kampala): under construction, target 2027. Katosi (Mukono) and Greater Kampala The Katosi Water Treatment Plant in Mukono produces about 160 million litres a day, but transmission limits prevent full use. The Package 2B expansion, financed by AFD, KfW, the EU and the EIB, adds about 70 km of transmission mains, reservoirs at Kanyanya, Kabulengwa and Mutungo, and 1,400 prepaid public standpipes. The Kiira-Kasangati line is due by December 2026 and the full project by July 2027.
- Seed secondary schools (UgIFT): under construction. Nationwide (sub-counties without a government secondary school) Under UgIFT, government is building 259 seed secondary schools in sub-counties that have no government secondary school. The programme page reports 117 completed in Phase I and 77 commissioned and operational. The programme also upgrades 1,000 primary schools and recruits teachers.
- National ID mass registration and renewal: delayed. Nationwide NIRA ran a mass registration and renewal drive from May 2025. By 7 September 2026 it had printed 15.4 million new IDs, of which only 10 million had been issued, leaving about 5.4 million uncollected. NIRA estimates 10.9 million Ugandans remain unregistered and 6 million have not renewed expired IDs. It has asked to grow its staff establishment from 571 to 998.
- National Backbone Infrastructure Phase V: under construction. Nationwide, including Karamoja Phases I-IV of the NBI laid 4,387 km of fibre, connecting 53 district headquarters, 11 border posts and 1,480 government agencies. Phase V, launched in December 2024 and funded by China Exim Bank, will add 5,845 km of fibre to 63 more districts, last-mile links to over 2,800 sites and 1,754 Wi-Fi sites. We found no verified 2026 progress figures.
- Parish Development Model (PDM): operational. Nationwide (all parishes) Each verified parish SACCO receives UGX 100m a year in two UGX 50m instalments. By November 2025 total transfers had reached UGX 3.216 trillion across 10,589 SACCOs, reaching about 3.27 million beneficiaries. District reports show uneven loan recovery; for example, Monitor reported UGX 5m recovered in Kalaki out of about UGX 12bn disbursed.
- Coffee exports at record levels: operational. Nationwide (Masaka, south-western, central and Elgon growing areas) In the 12 months to March 2026 Uganda exported 8.8 million 60-kg bags of coffee worth USD 2.4bn, up from 6.9 million bags worth USD 1.8bn a year earlier. In March 2026 export volumes rose but earnings fell 13.6% as world prices declined. Robusta makes up most shipments, and Italy is the largest market.
- Kampala Industrial and Business Park, Namanve: under construction, target 2026. Namanve, Mukono District (Greater Kampala) A EUR 215m infrastructure project in the 2,400-hectare Namanve park, covering roads, drainage, power, water, fibre, street lights and CCTV, was 80% complete in July 2026. Completion has been extended to 30 December 2026. It is financed by the Government of Uganda, UK Export Finance and Standard Chartered and built by Lagan DOTT Namanve. The park hosts about 480 factories, of which nearly 280 are operating.
- Wagagai gold mine, Busia: operational, stated cost USD 250 million, target 2025. Alupe, Busia District President Museveni commissioned the Chinese-owned Wagagai gold mine in Busia District in August 2025. It is Uganda's first large-scale gold mine, with an investment reported at USD 250m. At full capacity it is expected to process 5,000 tonnes of ore a day and produce about 1.2 tonnes of refined gold a year.
- Muko iron ore and local steelmaking: planned, stated cost USD 500 million. Muko (Kabale and Kisoro); steel plant in Jinja The Muko iron ore deposit in Kabale and Kisoro holds about 150 million tonnes, and developing a mine is projected to cost about USD 500m. In January 2025 the Abyssinia steel plant in Jinja was commissioned to use Muko ore, and a direct reduced iron plant run by Tembo Steels was inaugurated. Uganda has banned unprocessed iron ore exports since 2015.
- 2026 general election result: completed, target 2026. Nationwide; national tally centre at Lubowa Presidential, parliamentary and local elections were held on 15 January 2026. The Electoral Commission declared Yoweri Museveni the winner with 7,946,772 votes (71.65%), ahead of Robert Kyagulanyi (NUP) with 2,741,238 (24.72%). Turnout was 52.50%: 11,366,201 ballots from 21,649,067 registered voters. Kyagulanyi rejected the results.
- National budget FY 2026/27: operational, target 2027. National Finance Minister Henry Musasizi read the FY 2026/27 budget on 11 June 2026. Total resources are UGX 84.39 trillion, of which UGX 44.18 trillion comes from domestic revenue. Government projected about 10% growth for FY 2026/27, linked to the start of oil production, which has since been pushed to June 2027.
- Five pending cities (Entebbe, Wakiso, Kabale, Moroto, Nakasongola): delayed. Entebbe, Wakiso, Kabale, Moroto, Nakasongola Parliament approved 15 new cities on 28 April 2020. Ten became operational on 1 July 2020: Arua, Fort Portal, Gulu, Hoima, Jinja, Lira, Masaka, Mbale, Mbarara and Soroti. Government announced that Entebbe, Wakiso, Kabale, Moroto and Nakasongola would gain city status on 1 July 2025, but reports from August 2025 said they had not yet taken effect.
- AFCON 2027 stadiums (Mandela, Hoima, Akii-Bua): under construction, target 2026. Namboole (Kampala area), Hoima City, Lira City Uganda will co-host AFCON 2027 with Kenya and Tanzania from 19 June 2027, using three venues. In September 2026 Hoima City Stadium upgrades were about 95% complete, Akii-Bua Stadium in Lira about 80%, and Mandela National Stadium was on track for December 2026. The 20,000-seat Akii-Bua stadium is being built by SAMCO for about UGX 470bn.
- International tourist arrivals 2025: operational. Nationwide International visitor arrivals rose to about 1.6 million in 2025 from about 1.37 million in 2024, according to the Ministry of Tourism's 2025 statistical abstract as reported by NTV. Government's medium-term goal is 2.2 million arrivals.
Source: Government ministries and agencies, project companies, development banks and national press, as listed on each project. Published on Pearl Insights (https://pearl-insights.org), an independent civic data platform, not an official government website.